Project Timeline and Cost
Timeline
The estimated time for completing upgrade process is around 12-14 weeks.
| Task | Week |
|---|---|
Setting up a new server and installing the latest Open edX version | 2-3 |
| Applying customizations to the new server | 1-2 |
| Data migration and testing | 1 |
| Upgrading iOS and Android apps | 4 |
| Testing and Quality Assurance | 2 |
| Final review and cutover | 1 |
| Final Deployment and Post-upgrade support | 1 |
Cost
The estimated cost for this project is $6,000 USD.